Compiled by Nicole Davis Indianapolis: As Citizens Energy Group continues to make progress on its DigIndy Tunnel System, upcoming construction will require the closure of E. Pleasant Run Parkway S. Dr. between N. Webster Ave. […]

Articles

Southside construction update

December 1, 2022 SST

Compiled by Nicole Davis I-69 Johnson County: Construction crews are completing the final steps needed to convert State Road 37 to Interstate 69 between Martinsville and Bargersville. Banta Road, near the Morgan-Johnson county line, was […]

Articles

Southside construction update

November 23, 2022 SST

Compiled by Nicole Davis I-69 Johnson County: The last bridge beams over the future I-69 will be delivered and staged early this week. Motorists should expect short stoppages on northbound S.R. 37 between Fairview Road […]

Articles

Southside construction update

November 17, 2022 SST

Compiled by Nicole Davis * I-69 Indianapolis: The new Southport Road bridge over the future I-69 is now open! It is one of the largest bridges on the I-69 Finish Line project. The new southbound […]

Articles

Southside construction update

November 10, 2022 SST

Compiled by Nancy Hammerstrom *I-69 Indianapolis Southport Road traffic will shift onto the new bridge over future I-69. The southbound S.R. 37 exit ramp to Southport Road will also open. The existing S.R. 37 traffic signal […]

Articles

Southside construction update

November 3, 2022 SST

Compiled by Nicole Davis * I-69 Indianapolis: The new Southport Road interchange for the future I-69 is expected to open partially next month. Crews are connecting the new and old roadways and shifted Southport Road […]

Articles

Southside Construction Update

October 27, 2022 SST

Compiled by Nicole Davis Southeast Indianapolis: I-65 safety and efficiency is expected to improve traffic flow and safety along I-65 on the Southeast side of Indy. The nearly 5-mile project corridor stretches from north of […]

Articles

Southside construction update

October 20, 2022 SST

Compiled by Nicole Davis * I-69 Indianapolis: The permanent looping ramp for northbound S.R. 37 exiting onto County Line Road is now open! It splits off from northbound S.R. 37 traffic about a half mile […]

Articles

Southside construction update

October 13, 2022 SST

Compiled by Nicole Davis * I-69 Indianapolis: Waterline work which started Oct. 10 will close lanes on northbound State Road 37/Harding Street and the I-465 interchange exit ramps between 8 a.m. and 4 p.m. each […]

Articles

Southside construction update

October 6, 2022 SST

Compiled by Nicole Davis * I-69 Indianapolis: Construction of the future I-69 interchange and lanes has closed Epler Avenue west of State Road 37. Drainage pipe installation will reduce Wicker Road to one lane near […]